top of page
Downsized Logo_edited.jpg

CONSERVATION

Arrow Down

PROJECT INFORMATION

Location

City / State

Address

GPS Coordinate

Ipoh, Perak

Jalan Bougainvillea A/1,

Bandar Seri Botani,

31350 Ipoh,

Perak Darul Ridzuan

(Behind BHP station of Bandar Seri Botani).

Latitude

4.52911 

Longitude 

101.10378 

Details

Client

Consultant / Architect

Date & Duration of Project

Jabatan Agama Islam dan Istiadat Melayu Negeri Perak

ATSA Architects Sdn Bhd

11th April 2016 –

20th February 2018

Contractor

Conservator

Project Cost

Shane Global Services

Dr. Jaki Mamat &

Ar. Azim A. Aziz

500,000.000 MYR

PROJECT SYNOPSIS

The Relocation, Conservation & Preservation of Kampung Teluk Memali Mosque in Kg. Gajah, Perak to Ipoh, Perak

A breakthrough conservation attempt spearheaded by ATSA Architects has made it possible for this unique traditional Perak Malay mosque structure.  Abandoned for the past 20 years, the derelict structure, known to the Kampung Gajah in Perak folks as the Kampung Teluk Memali Mosque, was built in 1910, near the banks of the Perak River. The mosque has now been serving the local Muslim community of Taman Seri Bougainvillea in Bandar Seri Botani, Ipoh, Perak. 


Prior to the relocation work stage, timber identification test and dilapidation survey were conducted by the respective Malaysian Timber Industry Board (MTIB) and registered conservator consultants. The results of the study shown that the 108-year-old mosque was structurally sound, without many damaging and structurally defects. 


Later on, the dismantling work commenced with early preliminary works that involved site clearance and preparation, coding and numbering of each wooden component and the transfer of the old mimbar to a safer location. The dismantling works began on the next day with the relocation of the old kolah (ablution) tank to the new site using a crane and loader. 


Next, the workers started to disassemble building components carefully, beginning with the roof structure that consisted of zinc and asbestos free sheet roofing, fascia boards, purlins, rafters, trusses and so on. After the roof structure was completed, wall panels and tie beams were dismantled, followed by a series of columns, including the main and supporting columns. 


Furthermore, all bundled components were transported to the new site using lorry, which had been sorted according to their elements. For the next process of treatment and replacement of wood components, they were brought to a timber workshop located in Chemor, Perak, while some others were brought and stored on site, underneath a canopy tent. At the same time, new replacement timber components were made to order in a factory in Terengganu which was transported to the new site later.  


The final roof finish, the singgora tiles were laid on the roof structure, on top of the roof purlins. The reinstallation works then continued with internal and external works, such as the timber ceiling strips, decorative wall panels, painting works, fascia board, lattice arch, serambi and window balustrade, reconstruction of anjung and installation of timber flooring in the main prayer hall.

 

All of these works, including the construction of the new balai lintang and electrical wiring were finished in March 2017. While by September 2017, the toilet building and landscape elements were fully completed on site. 

CONSERVATION TIMELINE

Before
Conservation

before 1.png
before 1.png

FRONT VIEW

APR 2016

before 3.png
before 3.png

INTERIOR VIEW

APR 2016

before 5.png
before 5.png

SIDE VIEW

APR 2016

before 7.png
before 7.png

KOLAH (ABLUTION POOL)

APR 2016

11th April

2016

before 2.png
before 2.png

SIDE VIEW

APR 2016

before 4.png
before 4.png

SIDE VIEW

APR 2016

before 6.png
before 6.png

ROOF WITH SINGGORA TILES

APR 2016

before 8.png
before 8.png

MINBAR

APR 2016

during 1.png
during 1.png

DISMANTLING ROOF STURCTURES

during 3.png
during 3.png

DISMANTLING BUILDING COMPONENTS FOR RELOCATION

during  5.png
during  5.png

BASE CONSTRUCTION AT NEW SITE IN CHEMOR

during 7.png
during 7.png

RESTORATION OF BUILDING COMPONENTS

during 9.png
during 9.png

REINSTALLATION OF INTERNAL BUILDING COMPONENTS 

during 11.png
during 11.png

CONSTRUCTION OF NEW BALAI LINTANG AND ELECTRICAL WIRING
MAC 2017

During
Conservation

during 2.png
during 2.png

DISMANTLING BUILDING COMPONENTS FOR RELOCATION

during  4.png
during  4.png

SITE CLEARANCE AT NEW SITE IN CHEMOR

during 6.png
during 6.png

BASE CONSTRUCTION AT NEW SITE IN CHEMOR

during 8.png
during 8.png

RESTORATION OF KOLAH

during  10.png
during  10.png

SINGGORA TILES LAID ON ROOF STRUCTURE

during 12.png
during 12.png

COMPLETION OF LANDSCAPE ELEMENTS

SEP 2017

after 1.png
after 1.png

FRONT VIEW 

after 3.png
after 3.png

KOLAH

after 5.png
after 5.png

INTERIOR VIEW

after 7.png
after 7.png

INTERIOR VIEW

After
Conservation

20th February

2018

after 2.png
after 2.png

FRONT VIEW

after 4.png
after 4.png

SIDE VIEW

after 6.png
after 6.png

INTERIOR VIEW

after 8.png
after 8.png

EXTERIOR VIEW

OTHER RESOURCES

Related Link /
Website

Official Website

KPG MEMALI MOSQUE
Memali Mosque info
Memali Mosque Synosis
Memali Mosque Timeline
Memali Mosque Others
Memali Mosque During Cons.
Memali Mosque After Cons.

All contents of PAM-eR excluding publicly sourced documents are Copyright © 2023 Pertubuhan Akitek Malaysia. All rights reserved.

bottom of page